Guide · Based on the 41-update remodel diary (2003–2004)

Lessons from a six-month whole-house remodel, lived in

From November 2003 through May 2004, the Sherwoods remodeled their 1960s-era San Diego home — a new second story, expanded kitchen and family room — while living in it the entire time. What follows is the short version of what it taught them, drawn straight from the 41 photo updates of the remodel diary.

  • Living in the house during construction is possible — with plastic walls, patience, humor, and a contractor your dog likes. Dancer and Craig got along famously, which let everyone escape when the saws started.
  • Milestones happen when relatives visit. Nana watched the concrete pour; Uncle Ken saw the steel beam fly. Invite people; the house will perform.
  • Photograph everything, even (especially) the tedium. Two tar strips, a leaking wall, a displaced Dancer — the "boring" days tell the real story.
  • Refinance-and-remodel timing matters: the family started in wildfire season 2003, competing for crews and materials with hundreds of rebuilding neighbors. Add slack to any estimate you make.
  • Small tools for big jobs are a humiliation: Keith's suburban rake-and-shovel collection never once won against a baseball diamond or a foundation trench.

What a live-in remodel actually looks like

Every other week for six months, the diary recorded the same rhythm: dust, decisions, a milestone, then the slow re-clean of the "clean half" of the house. The payoff — a kitchen with granite, a family room everyone fits in, and a bedroom with a view — got used so long it was almost forgotten it had ever been otherwise.

The diary preserves a level of detail no photo album would: the tar strip you couldn't walk on, the dog's opinion of jackhammers, the stove carried out the front door. Start at the baseline (November 22, 2003), or jump to move-back day.

Key moments, in order

  1. Baseline, November 2003

    Before the first hammer swing: photographs of the house as-was, the numbers, and the loan that started it all.

  2. Jackhammers and new footings (January 2004)

    The old patio came out by jackhammer. The dog did not approve. The new foundation went in footings-first.

  3. The 1,600-pound steel beam (January 2004)

    A steel I-beam — 1,600 pounds of it — was lifted and installed to carry the second floor. Visiting family got to watch.

  4. New rooms above (February–March 2004)

    Bedrooms, a deck, and a new view: the second story takes shape while the family lives below it.

  5. Kitchen month (March–April 2004)

    Cabinets, counters, appliances: the kitchen rises from a plastic-walled zone into the heart of the house.

  6. Granite and final rooms (April 2004)

    Granite counters, carpet, paint and stucco — the finish line appears.

  7. Tile week (May 2004)

    Tile goes down on two-thirds of the bottom floor; nobody is supposed to walk on it. Nobody does. Mostly.

  8. Move-back day (May 9, 2004)

    Old appliances return, new ones arrive, and the Sherwoods get a kitchen back — six months after the first jackhammer.